Quick Answer
Calculate CPI-Based Forecast at Completion (FAC) for Project Cost Performance
Calculator
Need Equipment or a Supplier for This Project?
Use your calculation result to continue with equipment selection, supplier discovery, engineering support, or project evaluation.
Find Engineering Solutions →Result Interpretation
CPI-Based Forecast at Completion (FAC) for Project Cost Performance calculator computes Forecast at Completion in USD using the defined engineering formula and the input values provided. Forecast at Completion is expressed in USD. No universal acceptance threshold is defined by this calculator.
Worked Example
Verified calculation
Given:
- Budget at Completion = 100000
- Earned Value = 40000
- Cost Performance Index = 0.95
- Actual Cost = 42105.26
Expected Result:
- Forecast at Completion = 105263.15473684
Engineering Interpretation:
Under the given input conditions, the calculated result is: Forecast at Completion = 105263.15473684 USD.
The actual numerical result is computed by the Runtime engine using the persisted tool definition. The values shown here come from deterministically validated test cases.
Formula / Method
forecast at completion = (budget at completion - earned value) / cost performance index + actual costFormula family: formula_project_forecast_at_completion_fac_cpi_based_calculator
Variables
| Symbol | Label | Role | Description |
|---|---|---|---|
| budget_at_completion | Budget at Completion | INPUT | Budget at Completion |
| earned_value | Earned Value | INPUT | Earned Value |
| cost_performance_index | Cost Performance Index | INPUT | Cost Performance Index |
| actual_cost | Actual Cost | INPUT | Actual Cost |
| forecast_at_completion | Forecast at Completion | OUTPUT | Forecast at Completion |
Calculation Steps
- Enter the budget at completion in USD.
- Enter the earned value in USD.
- Enter the cost performance index in dimensionless.
- Enter the actual cost in USD.
- Step 1: Compute forecast at completion.
- Read the forecast at completion (USD) from the results.
Engineering Summary
Calculate CPI-Based Forecast at Completion (FAC) for Project Cost Performance
Frequently Asked Questions
What does this calculator calculate?
The CPI-Based Forecast at Completion (FAC) for Project Cost Performance calculator estimates Forecast at Completion based on the input parameters you provide
Why is budget at completion important in this calculation?
budget at completion is directly proportional to forecast at completion. When you enter budget at completion in USD, the calculator uses it in the engineering formula to compute the output
How should I interpret the result forecast at completion?
The calculator outputs forecast at completion in USD. The result is computed directly from the input values using the defined engineering formula
What units should I use for the inputs?
Enter each value in the units shown next to the input field: Budget at Completion (USD), Earned Value (USD), Cost Performance Index (dimensionless), Actual Cost (USD). Make sure all inputs use the specified units for consistent results
What assumptions does this calculator use?
This calculator uses automatically validated engineering formulas. Results are approximate and should be validated against site-specific conditions, applicable codes, and professional engineering judgment